EcoDrilling UDR 650, Central Otago

Mineral permits · Methods

Checking an NZPAM exploration work programme

A consistent geological rationale, staged programme and costed plan help an applicant propose work that can actually answer the exploration question.

NZPAM · Practical method · 11 October 2026

Start with the geological uncertainty

Before writing a permit application, identify the decision the first stage of fieldwork must support. A field method and its proposed quantity should follow from the evidence that is currently missing. Mapping or surface sampling may be appropriate for an exposed structure; where the target is concealed, the programme may need geophysics, pits or drilling to test the model.

Check the commitments as one set of numbers

A permit-area map, work-programme schedule and financial estimate should use the same activity quantities. Check the number and expected depth of drillholes, access and mobilisation, geological supervision, sample preparation and laboratory analyses, rehabilitation and reporting. Record whether metres, holes and costs represent minimum commitments or indicative planning allowances. A programme is less useful if the geological rationale and the proposed spending describe different work.

Show who will do the work

NZPAM's current application guidance asks for supporting information on proposed work programmes and the applicant's technical and financial capability. The proposed operator must have appropriate experience or access to qualified people to deliver the activities. Qualifications and subcontractor availability should be tied to the actual methods, field conditions and planned scale rather than described in generic terms.

Reconcile the application before lodgement

Check commodity and boundary descriptions, location maps, geological references, work phases, minimum quantities, budget, operator responsibilities and attachments. Where review identifies a contradiction, revise both affected sections. Keep a source register and a version record so responses to regulator requests can be traced to the submitted programme.

The programme should also distinguish mineral tenure from land access and other approvals. Wairiri prepares geological and work-programme material, but neither a favourable geological case nor a complete application guarantees a permit.

Official material

NZPAM — Apply for a new minerals permit identifies application steps and supporting material. The Minerals Programme for Minerals (Excluding Petroleum) 2025 sets out assessment principles for different minerals permits. Use the official current documents for a live application.

Wairiri NZPAM application services · Back to insights